按照瑞典圆弧法 ,对某大堤在施工竣工期和稳定渗流期的抗滑稳定性进行了验算 ,并提出大堤施工建议。
Based on the Sweden analysis method,checking to the stability of countermeasures of landslide in construction finish time and stabilization seep time in some levee was performed,and the levee construction recommendations were given.
出处
《电力勘测设计》
2000年第3期37-40,共4页
Electric Power Survey & Design
关键词
大堤
瑞典园弧法
稳定性
levee
Sweden analysis method