柴河水库“05·8”洪水尾水渠抢险技术措施及修复方案 被引量:1

The technique measure for the rush to deal with the flood in the trail channel of Caihe reservoir on August of 2005 and relating rehabilitating scheme
下载PDF
导出
摘要 就尾水渠抗洪抢险过程中采取的放大树作支挡骨架,抛石笼挡水,堆砂袋充填加固及采用的角钢联结加固办法,通过应用证明所采取的技术措施与对策可行且效果较好,对同类工程的抢险和处理具有借鉴意义。同时在尾水渠的修复中有些技术问题的处理上,采取了相应的技术措施和处理办法。 during rush to control the flood in the trail channel,big trees are used to be framework,jacking gabion are used to be block flood, piling sand bags are used to strengthen them and angle iron are used to united them,the practice indicates the technique measure is effect and benefit,it can provide reference for the same kinds of projects.Simultaneity during the rehabilitation of the trail channel,the relevant technique measures and handling method are used.
出处 《吉林水利》 2007年第2期42-43,共2页 Jilin Water Resources
关键词 尾水渠抢险 修复方案 技术措施 rush to control the flood technique measure gabion coupling
  • 相关文献

同被引文献10

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部