摘要
文章介绍了张石高速北口隧道软弱破碎围岩段支护方案的优化过程。通过采用现场监控量测法对优化方案进行动态监测,其结果与数值模拟结论基本吻合,表明隧道处于稳定状态,施工与支护方案合理。
The article introduces the optimizing process of a support plan,which is designed for the soft breaking adjoining rock on north tube of Zhangshi highway tunnel.With the ambulatory monitoring on this plan by on-the-spot monitor measuring,the data turned out basically the same with the result of numerical modeling,which shows that the tunnel is stable and also,the construction and support plan is rational.
出处
《西部交通科技》
2008年第4期49-52,共4页
Western China Communications Science & Technology
关键词
支护
优化方案
动态监测
数值模拟
Support and protection
Optimizing plan
Ambulatory monitoring
Numerical modeling