摘要
介绍了莱钢焦化厂 5 8- 型焦炉燃烧室单面墙吊顶翻修过程中的温度控制方法 ,对焦炉大面积翻修后的快速升温尝试采用干燥期和升温期两段升温方式 ,使升温时间由 3 0天缩短为 9天 ,保证了该修补炉号安全和尽快恢复生产。
The method of the temperature control in the overhaul procedure for the suspended ceiling of single wall of combustion chamber of type 58-Ⅱ coke oven in the Laigang coke plant is introduced The heating way for two stages of drying period and heating period is tried for quick heating of coke oven after overhaul with big area The heating time has been reduced from 30d to 9d The overhaul security of oven and resuming the production as soon as possible has been ensured
出处
《山东冶金》
CAS
2002年第2期16-18,共3页
Shandong Metallurgy
关键词
焦炉
燃烧室
翻修
温度控制
coke oven
combustion chamber
overhaul
temperature control