摘要
50 0kV输电线路拉V塔整体移位 ,使用 9m抱杆将铁塔吊在专用底座上 ,用 8根临时拉线防止铁塔过度倾斜 ,用双绞磨滑轮系统将整个铁塔顺线路铺设的铁板轨道拖至新塔位。
The author illustrates the integral displacement of a guyed-V tower on 500 kV transmission line. First, 9 m holding poles are used to lift the whole tower onto the special pedestal and 8 pieces of temporary guys are used to prevent the tower from excessive tilt. The double-winch pulley system pulls the whole tower to the new position on the iron plate railway laid along the line.
出处
《电力建设》
北大核心
2002年第9期30-32,共3页
Electric Power Construction
关键词
500kV拉V塔
整体移位
施工方法
kV guyed V tower
integral displacement
construction method