摘要
分析了现行耐张转角塔分坑施工方法存在的弊端,提出了解决原理,并给出具体计算方法。
In this article the author analyzed some malpractices which exist in the present pit - divided construction method, advanced resolving principle for these question, and gives a concrete calculation method.
出处
《广东输电与变电技术》
2004年第2期31-33,共3页
Guangdong Power Transmission Technology
关键词
耐张转角塔
扭转偏差
分坑原则
应力状态
Strain - resistant corner tower Turn deviation Pit - divided principle Stress state