摘要
本文通过跟踪、总结金汉拉扎电站转轮设计制造过程中出现的难题和解决的过程,对高水头小型水轮机转轮的设计制造优化提出一些建议和看法,为相近电站转轮的设计提供参考。
The methods and advices on design and manufacture of high head Francis turbine by tracking the design and manufacture procedures of small size runner of Jinhanlazha project were introduced in this paper;it can be a reference to design similar runner.
出处
《大电机技术》
北大核心
2010年第2期41-44,共4页
Large Electric Machine and Hydraulic Turbine
关键词
高水头
水轮机
转轮
设计
high head
hydraulic turbine
runner
design