介绍了小山水电站厂房上游排水廊道渗漏水、结露水的治理方案,由于采用的新材料和新工艺,彻底解决了水电厂的渗漏水和结露水问题。
Governance programs for the hill hydropower plant upstream drainage corridor seepage of water and dewing is presented.With the use of new materials and new techniques,the leakage of water and the hydropower plant dew problem are completely solved.
出处
《电力技术》
2010年第2期42-44,共3页
Electric Power Standarization & Construction Cost Control Information
关键词
水电站
渗漏水
结露水
治理
Hydropower station
Seepage of water
Dew
Treatment