摘要
结合双电公司2台国产600 MW超临界机组凝结水系统的调试与运行中出现的问题,通过分析提出凝结水系统相关问题的解决方法。
Analyzing the problems arising from the commissioning and operating of condensate system of the two 600MW units made in China in Shuangyashan Power Company,this paper proposes solutions on relative problems of condensate system.
出处
《黑龙江电力》
CAS
2010年第3期219-221,共3页
Heilongjiang Electric Power
关键词
汽轮机
凝结水
调试
turbine
condensate water
commissioning