锅炉SCR烟气脱硝空气预热器堵塞原因及其解决措施 被引量:115

AIR PREHEATER BLOCKING IN BOILER WITH SCR DENITRIFICATION DEVICE:REASON ANALYSIS AND SOLUTIONS
下载PDF
导出
摘要 分析锅炉进行SCR烟气脱硝时空气预热器冷段元件硫酸氢氨堵塞的原因,认为其主要因SCR装置过量喷氨或局部过量喷氨造成大量氨逃逸所致。对此,提出对于运行效果较差的空气预热器,可结合降低排烟温度或者漏风率进行其换热元件的综合改造等措施。同时,建议空气预热器冷段换热元件在煤中硫含量较低以及出口综合温度较高时采用高性能的考登钢材质。 Heat transfer elements of preheater on boiler with SCR denitrification equipment were blocked by ammonium bisulfate(ABS).Large amount of ammonia escaping caused by excessive ammonia injection in SCR equipment or it's local area was considered as the main reason.Thus,comprehensive retrofit for heat transfer elements of preheater with bad operation effect should be conducted,combining with decreasing the exhaust gas temperature or air leakage rate.Meanwhile,the heat transfer element for cold segment of air preheater should be made of Corten steel,for the low sulfur content coal,or high outlet integrated temperature.
出处 《热力发电》 CAS 北大核心 2012年第8期45-47,50,共4页 Thermal Power Generation
关键词 烟气脱硝 空气预热器 氨逃逸 硫酸氢氨 堵塞 flue gas denitrification air preheater ammonia escape ammonium bisulfate block
  • 相关文献

参考文献4

  • 1宋玉宝.SCR设计与烟气参数耦合性分析,2012.
  • 2John Guffre.Eliminating Air Heater Plugging and Corrosion Caused by SCR/SNCR Systems for NOx Control on Coal Fired Boilers,2007.
  • 3Heinz Gutberlet.GTZ-Seminar on SCR-DeNOx technology,2010.
  • 4梁衡.SCR空气预热器改造方案设计与实施要点,2011.

同被引文献678

引证文献115

二级引证文献521

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部