摘要 针对仙人岩水电站的双绕组电抗分流励磁装置技术水平低、故障率高、并网运行不稳定等问题,选择静止式可控硅半控桥自并激励磁系统进行了技术改造。实际运行结果表明,改造后励磁系统的电压调节范围大,当电网电压波动时发电机的无功功率变化小,在每一区间均能稳定运行。 Aiming at the problems of low technical level,high failure rate,instable grid operation and the like of double winding reactance shunt excitation device in Xianrenyan Hydropower Station.Static thyristor half-controlled bridge self-grid excitation system is adopted for technical reconstruction.The practical operation result shows that after reconstruction,the voltage adjustment range of the excitation system is large,when the grid voltage is fluctuated,the generator reactive power has small change,and it can stably operate in each interval.
作者 朱朝晓
出处 《中国水能及电气化》 2012年第12期46-49,共4页 China Water Power & Electrification
关键词 小型水电站 发电机 励磁系统 技术改造 small hydropower station generator excitation system technological reconstruction
  • 相关文献

参考文献3

  • 1许建安.水电站自动化技术[M]北京:中国水利水电出版社,2006.
  • 2许建安.电力系统微机继电保护[M]北京:中国水利水电出版社,2001.
  • 3许招才.低压水轮发电机组运行与维修[M]北京:中国计划出版社,1999.

同被引文献24

引证文献4

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部