摘要
重点阐述了新型顶模棍垫块的结构构造、使用方法,新型顶模棍垫块使用可以顶替传统施工工艺中的顶模棍.传统剪力墙模板安装时都会按施工组织设计在剪力墙的上下焊接和剪力墙厚度相同的顶模棍,施工过程较为繁琐,此新型顶模棍的使用加快了施工进度,节约了材料.
This article focuses on the structure and applging method of the new-type top-mold stick block,Which can replace the old top-mold stick in traditional construction techniques.In the process of traditional installation of wall template,according to the construction organization and design,and the top-mold stick of the same thickness as the wall will be welded at the top and end of the wall.Which is more cumbersome.Incontrast,the application of the new-type top-mold stick can speed up the construction schedule and save materials.