摘要
兰州西固热电厂165MW机组循环水系统为母管制运行方式。其水泵出口门为低位置电动门,循环水坑水位高时有水淹危险,存在安全隐患。针对此问题对循环水系统进行整改,并将循环水系统逻辑进行优化。
The operation mode of circulating water system in 1 6 5 MW unit Lanzhou Xigu Thermal Power Plant is main-pipe scheme.The electrically operated outlet valve is in a low position,and when cir-culating water level rises,there is a flooding risk.To solve this problem,corrective measures and logic optimization for circulating water system were proposed.
出处
《河北北方学院学报(自然科学版)》
2013年第6期21-23,共3页
Journal of Hebei North University:Natural Science Edition
基金
张家口市科学技术和地震局指导项目(1221018B)
河北北方学院自然科学研究青年基金计划项目(Q2013003)
关键词
循环水
系统
逻辑
优化
circulating water
system
logic
optimization