摘要
综采移变泵站设备大,连接的电缆、供液管路多,串车长度大,外移需整体运动,要从有皮带搭接设备占位且正常运转的"丁字"口转弯绕行外移出来,难度比较大。针对该问题,通过研究分析,提出了解决该问题的技术手段,现场实施后效果良好,为其他类似情况提供了借鉴经验。
There were lots of large pumping equipments, cables and supply pipes in mechanized mining. String carhad long length and required overall movement while relocation. But it was difficult to turn bypass "T"port. Aiming at this problem, through research and analysis, the solution to the problem was put forward, the good effect was gained, which provided a referential experience for other similar situation.
出处
《煤炭与化工》
CAS
2013年第7期92-94,共3页
Coal and Chemical Industry