期刊文献+

工期索赔的处理原则与方法

Claims processing principle and method
下载PDF
导出
摘要 工期索赔的根本原因在于合同双方延误造成,根据承包商审报并经监理人审批的基线施工进度计划,计算关键线路和非关键线路的总时差,分析延误事件的背景,依据工程建设合同条款界定合同双方责任,及时妥善的处理好工期索赔乃至相关费用索赔问题。 The claim for extension of time is the fundamental cause of delays caused by both parties of the contract,the contractor and supervision according to the trial by the examination and approval of the person baseline construction schedule,calculate the critical line and the critical line of the total float,analysis of the delay to background events,according to the engineering construction contract terms defined the two parties of the contract liability,timely and properly handle the claim for construction time and costs associated with claims problem.
作者 李嘉良
出处 《建筑监督检测与造价》 2011年第6期47-51,共5页 Supervision Test and Cost of Construction
关键词 施工延误 基线进度计划 动态更新 赢得值法 construction delays baseline schedule dynamic update earned value method
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部