根据地形特点,大红山铜矿总回风竖井工程采用了无井架施工技术。利用井颈段的钢筋混凝土井壁作为凿井井架,稳绞设备布置具有较好的灵活性,同时减少了钢制凿井井架的设备投入,取得了良好的经济效益。
According to the terrain,the non-derrick construction technology was applied to the total return air shaft of dahongshan copper mine.The upside reinforced concrete was used as a drilling derrick,this technology gained the better flexibility of equipment layout and the less capital input of derrick and the better economic benefit.
出处
《金属矿山》
CAS
北大核心
2009年第S1期417-418,共2页
Metal Mine
关键词
大直径
竖井
无井架施工技术
Large diameter
Mine shaft
Non-derrick construction technology