阐述了在对125 MW机组厂用电切换装置改造过程中,对备用电压的接入,ATS运行方式的设定,设备选型等问题的注意事项。
To the process of reconstructing the device of electrical switching in 125MW unit station, some relevant problems should be concerned, for example, switching in standby voltage, adjusting ATS acting and selecting equipment, ect.
出处
《电力系统保护与控制》
EI
CSCD
北大核心
2003年第S1期57-58,共2页
Power System Protection and Control
关键词
ATS
快速切换
相位
单片机
ATS
fast switching
phase
single-chip processor