摘要
本文分析了伊、洛河上引水式水电站低坝引水枢纽中冲沙闸在设计布置方面存在的主要问题,论述了现行计算方法应用于山区河流引水枢纽中冲沙闸设计的局限性,提出了根据天然河道稳定主槽宽度、冲沙闸和冲沙槽的冲沙及沉沙要求进行冲沙闸设计计算的新方法,并通过算例的计算,证明了该计算方法的合理性。
The main problems existing in design and management of the flashing gate among the low dam approach hinges of approach water power station on the Yi River and Luo River are analyzed.The limitation of present calculating method used in the flushing gate design among the approach hinges on the mountain area river is discussed. A new method is put forward according to the width of the natural and steady major bed,the need of sand-flushing and crurrent sand of the flushing gate and channel. This method is proved reasonable by calculation examples.
出处
《黄河水利职业技术学院学报》
1999年第2期6-11,16,共7页
Journal of Yellow River Conservancy Technical Institute
关键词
引水枢纽
冲沙闸
设计
approach hinges
flushing gate
design