论述了土石方松动控制爆破理论,并结合具体工程实例,介绍了铜陵电厂基坑红砂岩松动控制爆破,对钻眼、底板控制技术及非电导爆管起爆网络的敷设作了阐述。
Control blasting theories for earthstone work were reviewed, linking the theories with practice work of control blasting for fundational redsand rock in Tongling Power Plant, drilling in base, controlling technology for base, and laying Nonel network were analysised and discussed.
出处
《安徽建筑工业学院学报(自然科学版)》
1998年第3期35-38,共4页
Journal of Anhui Institute of Architecture(Natural Science)
关键词
红砂岩
松动控制爆破
非电起爆网络