介绍了红枫发电总厂官厅型10MW水电机组改造增容为12MW(厂家设计增容值)的具体内容及碰到的重大技术问题和解决办法,并着重阐述了增容后机组的出力和效率问题.
The capacity up of the 10-MW turbine-generator set of Guaming type installed in Hongfeng Hydropower Station was be enlarged up to 12-MW. The detail, and main technology and using methodology of the modification and enlargement are introduced in the paper; The writer also discusses the output and efficient of the set after modification and enlargement.
出处
《贵州水力发电》
1996年第3期38-42,62,共6页
Guizhou Water Power
关键词
官厅型10MW机组
改造增容
问题
MW turbine-generator set of Guanting type, modification and enlargement, issue