期刊文献+

叶茂水电站施工组织设计的优化

Optimization Design For Construction Arrangement Of Yemao Hydropower Station
下载PDF
导出
摘要 论述在优化叶茂水电站施工组织设计中:简化临建设施、缩短施工准备期的措施;对过水围堰及其防洪标准的选择;场内外交通及供风、供水、供电方式;砂石系统优化和混凝土拌和系统布局;弃碴场利用等。并提出施工期取水及环境保护应计入概预算中。 This paper introduced optimization design for construction arrangement Yemao Hydropower Station, describing measure of simplifing temporary buildings which can shorten construction preparation period;design of overflow cofferdam and selection of its flood control standard;layout of transport in and out the site. means of supply of wind, water and electricity; optimization of sand and broken stone system; layout of concrete production system and full use of debris dump field. Besides,it suggested the expense for water supply during construction period and environment protection should be included in the budgetary estimate.
出处 《贵州水力发电》 1996年第1期34-38,共5页 Guizhou Water Power
关键词 施工 组织设计 三通一平 过水围堰 环境保护 优化 design for construction arrangement overflow cofferdam environment protection during construction optimization
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部