摘要
广深准高速铁路有部分区段利用既有路基,根据技术要求,需加固补强。广深铁路运输十分繁忙,要在确保正常行车条件下进行基床加固,技术难度很大,如果限速运行或封锁线路,又会造成巨大的经济损失。本文系统全面地论述了为解决这些问题进行的试验研究和应用效果。
According to the technical demands, some sections of the existing road .bed in Guang-shen quasi-high--speed railway should be consolidated and reinforced. Guang-shen railway is very busy. So it is difficult in technique to reinforce the road bed under the regular driving. If liciting speed or closing the railway,it must cause a great economic loss. This report expounds the experimental study all-sidedly on how to solve these problems and its application effect.
出处
《铁道工程学报》
EI
1996年第2期300-306,共7页
Journal of Railway Engineering Society
关键词
广深准高速铁路
既有路基
加固
技术
Guang-shequasi-high-speed railway
existing road bed
reinforcement