摘要 本文对京九铁路五指山隧道施工通风中使用的技术、针对高地温、高污染采取的有效措施进行综述,并对搞好双线长大隧道施工通风提出建议。对长大双线隧道特别是有平行导坑的长大隧道施工通风有参考价值。 The construction ventilation technique, which was adopted during the construction of the Wuzhishan Tunnel on the Jing Jiu Railway Line,is the effective measure applied against the high ground temperature and the high pollutions.This technology has been described comprehensively in the paper ,and the suggestions for doing well the construction ventilation for the double tracked long tunnels are proposed. It is valuable as reference for the construction of the double tracked long tunnels ,especially for the long tunnels with parallel heading adits.
出处 《铁道工程学报》 EI 1996年第4期46-53,共8页 Journal of Railway Engineering Society
关键词 长大隧道 平行导坑 施工通风 long tunnel parallel heading adit construction ventilation