摘要
本文根据非自喷井钻柱测试(DST)的流动特点,采用国外Peres等人提出的压力历史分析法,用JPD软件解释了江汉油田8口井资料,比较了Peres法与霍纳法所得到的结果,讨论了两种方法出现直线段的时间,分析了Peres法的的适用条件,初步探讨了在处理DST资料时常常遇到的边界显示现象。
According to DST flow behavior of nonflow well, the paper uses JPD software to inte(?)prete eigth well data in Jianghan Oil Field with utilization of pressure history analysis given by Peres, and so on, compared the results obtained from Peres and Horner, discussed time of appearing straight line segment with two methods, analyzed the applicable conditions of Peres method and primarily inquired into the boundary appearance usually encountered in evaluating DST information.
出处
《油气井测试》
1992年第2期34-40,75,共8页
Well Testing
关键词
非自喷井
钻杆测试(DST)
压力历史
早期试井解释
边界
Non—llowing well, Driil stem test(DST), Pressure history, Well test interpretation of early—time segment, Boundary.