钢栈桥整体吊装与空中对接施工

Integral hoisting construction and overhead joint of steel trestles
原文传递
导出
摘要 某电厂工程钢栈桥运用整体吊装法施工,克服了大跨度钢结构运输及吊装的困难,阐述了施工原理,着眼于钢栈桥分段加工、现场拼装、吊装方案三方面内容,选择了正确的吊具工况,重点验算了钢丝绳的负荷、起吊高度、双机抬吊荷载率、起重臂安全几方面内容,各项技术指标均符合设计和规范要求. For construction of steel trestle of a power plant,the integral lifting method for construction is used to overcome the difficulties in transporting and hoisting large span steel structure.This paper describes the construction principle,focuses on the sectional processing,on-site assembly and hoisting of the steel trestle.With the correct lifting device working conditions chosen,it focuses on checking the wire rope load,hoisting height,double-crane lifting loading rate,crane arm safety,etc.Various technical indicators are in line with the requirements of design and standards.
出处 《武汉大学学报(工学版)》 CAS CSCD 北大核心 2013年第S1期362-364,共3页 Engineering Journal of Wuhan University
关键词 整体吊装 空中对接 现场拼装 integral hoisting overhead joint on-site assembly
  • 相关文献

参考文献2

共引文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部