摘要 某工业园区内的一栋多层通用厂房,建于2009年,钢筋混凝土框架结构。2010年进行结构改造,在楼层和屋面增加了大量实验设备,使用活荷载超过了原设计值。本文详细介绍了该改造工程设计中,框架柱、梁的加固方法和构造措施。该改造方法通过调整设备布置,减小对原有结构的影响,从而达到缩短施工周期、降低工程造价的目的,为类似工程提供参考。 A multi-story general plant in an industrial park was built with a reinforced concrete frame structure system in 2009. It was rebuilt in 2010. Because of adding a great deal of laboratory equipment on the floors and roofing,the live load exceeded the value of the original design. This paper gives out some key points of the structure rebuilding design,which involve the strengthening and construction methods of the columns and beams. This method decreased the impact on the existing structure through the arrangement of the adjustment device. It can reduce the construction period and cut down the construction cost. The design experience can be referred to similar engineering.
作者 赵斌骅
出处 《建筑结构》 CSCD 北大核心 2013年第S1期1393-1396,共4页 Building Structure
关键词 改造 加固 既有结构 框架结构 构造措施 rebuild strengthening existing structure frame structure construction measure
  • 相关文献

参考文献2

二级参考文献5

  • 1吴晓涵,吕西林.反复荷载下混凝土剪力墙非线性有限元分析[J].同济大学学报(自然科学版),1996,24(2):117-123. 被引量:35
  • 2同济大学土木工程防灾国家重点实验室.上海国际设计中心结构模型模拟地震振动台试验研究报告[R].上海:同济大学土木工程防灾国家重点实验室,2007.
  • 3吕西林.钢筋混凝土结构非线性有限元理论与应用[M].上海:同济大学出版社,2002..
  • 4DARWIN D, PECKNOLD D A. Analysis of RC shear panels under cyclic loading [ J ]. Journal of the Structural Division, ASCE, 1976, 102(2): 355-369.
  • 5尹超,周颖,吕西林.上海国际设计中心超限高层结构抗震分析[J].结构工程师,2008,24(6):80-84. 被引量:11

共引文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部