摘要
随着我国海上风电开发进程的加快,针对潮间带地区前期测风工作的需要,在考虑潮汐变化等因素的前提下通过对陆地上普遍使用的拉线式测风塔基础进行二次设计,以适应该类地区特点。再结合以往潮间带地区的施工经验,在节约、快速的原则下,顺利完成了潮间带地区的测风塔建设,保证了前期测风任务的顺利完成。
With the accelerating process of Chinese offshore wind power development,and the needs of wind power early wind engineering in intertidal zone,the authors considered the factors such as tidal variation,then re-designed the widespread use of the guyed tower foundation on the land,in order to be suited for intertidal zone. Combined with the construction experience in the intertidal zone,and the followed principle of saving and fast,this paper successful completed the construction of offshore anemometer tower in intertidal zone.
出处
《施工技术》
CAS
北大核心
2013年第S2期412-415,共4页
Construction Technology
关键词
海上测风塔
基础施工
潮间带
offshore anemometer towers
foundation construction
intertidal zone