摘要
介绍了彭水水电站在狭窄河道上布置垂直升船机,所采用的新技术可为在狭窄河道布置升船机及后期经济运行提供借鉴。
出处
《水电与新能源》
2013年第S1期20-21,40,共3页
Hydropower and New Energy
同被引文献9
-
1贺治林.垂直升船机在水电站中的应用[J].水电与新能源,2013,27(S1):59-61. 被引量:2
-
2GB 50135-2006,高耸结构设计规范[S].
-
3GB50009-2012,建筑结构荷载规范[S].2012.
-
4Nak Joon Choi, Sang Hyun Nam, Jong Hynn Jeong, et al. Numer- ical study on the horizontal axis turbines arrangement in a wind farm : Effect of separation distance o11 the turbine aerodynamic power output [ J ]. Journal of Wind Engineering and Industrial Aerodynamics, 2013(Z1): 11-17.
-
5Jang-Oh Mo, Amanullah Choudhry, Maziar Arjomandi, et al. Effects of wind speed changes on wake instability of a wind turbine in a virtual wind tunnd using large eddy simulatlont[ J ]. Journal of Wind Engineer- ing and Industrial Aerodynamics, 2013(Z1) : 38-56.
-
6黄本才,汪丛军.结构抗风分析原理及应用[M].上海:同济大学,2008.
-
7Richard P J, Hoxey R P. Wind pressures on a 6m cube[J]. Jour- nal of Wind Engineering and Industrial Aerodynamics, 2001(89) : 1553-1564.
-
8黄光明,凌云,朱国金.景洪水电站水力式升船机塔楼结构性态分析[J].河海大学学报(自然科学版),2008,36(4):505-510. 被引量:3
-
9林太举,朱翼挺.金沙江向家坝高坝垂直升船机[J].水力发电,2014,40(1):66-68. 被引量:15
-
1郭建刚.缆索吊悬拼钢拱架箱型拱桥施工——以龚溪口大桥为例[J].中华建设,2011(6):174-175.
-
2尹政兴,莫青松,王立平.重庆乌江彭水水电站三斧沱重件码头工程关键技术研究[J].中国水运,2011(12):48-49.
-
3杨荣先.彭水水电站船闸第6跨渡槽箱梁大型承重排架施工法综述[J].西北水电,2014(6):93-96.
-
4李春放.复杂地质条件下高边坡爆破施工控制技术[J].中国水运(下半月),2012,12(5):217-218.
-
5闫军,陈蓉强,李斌.索道桥设计探讨[J].水利建设与管理,2008,28(2):23-24. 被引量:1
-
6刘文,郭振华.乌江彭水水电站地下厂房开挖施工[J].云南水力发电,2009,25(B09):17-20.
-
7彭水水电站500t垂直升船机开始安装[J].四川水力发电,2008,27(5):24-24.
-
8朱卫军,何为,徐春子.彭水水电站施工期过坝运输设计[J].人民长江,2006,37(1):52-53. 被引量:1
-
9巴添,陈明栋,肖娟.彭水水电站原型观测试验分析与建议[J].科技信息,2012(23):57-57.
-
10彭仲元.行程检测系统在彭水升船机中的应用[J].水电与新能源,2013,27(S1):57-58.