芦岭煤矿穿层钻孔二次封孔技术及工艺研究 被引量:6

Study on Second Cross-measure Drilling Hole Sealing Technology and Process in Luling Coal Mine
下载PDF
导出
摘要 针对当前芦岭煤矿地压大、底板巷穿层钻孔预抽时间长及穿层钻孔瓦斯抽采浓度偏低的情况,对穿层钻孔二次封孔技术及配套工艺进行研究,确定了适合芦岭煤矿底板穿层钻孔孔群的二次封孔工艺。不同负压条件下二次封孔技术实施后,瓦斯抽采浓度能够提高15%以上,并至少能够维持103d;负压2.5kPa时,二次封孔技术实施后103d内,技术实施前后瓦斯抽采浓度平均提高50%;负压4.5kPa时,二次封孔技术实施后43d内,技术实施前后瓦斯抽采浓度平均提高54%。 Aiming at the problems of high ground pressure,long pre-drainage time of floor roadway cross-measure drilling hole,and low gas extraction concentration of cross-measure drilling hole in Luling coal mine currently,conducted a study on second hole sealing and matching technology to determine the second hole sealing technology suited for floor roadway drilling boreholes group in Luling coal mine.After the implementation of second hole sealing technology in different negative pressures,gas extraction concentration could be raised by more than 15%,and could be maintained for 103 days.When the negative pressure is 2.5kPa,within 103 days of the implementation of second hole sealing technology,the gas extraction concentration is raised by 50% averagely after the technology implementation.When the negative pressure is 4.5kPa,within 43 days of the implementation of second hole sealing technology,the gas extraction concentration is raised by 54% averagely after the technology implementation.
作者 王新琨 张荣
出处 《煤炭技术》 CAS 北大核心 2015年第5期170-172,共3页 Coal Technology
关键词 二次封孔 穿层钻孔 瓦斯抽采 second hole sealing cross-measure drilling hole gas extraction
  • 相关文献

参考文献2

二级参考文献21

共引文献123

同被引文献57

引证文献6

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部