网络协同制造是现代企业提升综合竞争力的重要方法。协作活动开展的首要环节之一就是把协作目标分解为多项子目标,子目标的执行与其发生的时间顺序直接关联。主要提出一种新的目标分解时序约束的描述方法和算法。把分解的子目标的时序关系用R_(before)“先于”关系来描述,并根据企业协作的特点对R_(before)“先于”关系细化为两个子关系:R_(s-before)“串行先于”关系和R_(p-before)“并行先于”关系。以此为基础建立了计算子目标的执行时间区间的逆向递推算法,并为目标分解粒度的确定、减少目标执行时各子目标之间的耦合度提供了时序约束角度的准则。该方法有效地解决了基于多Agent的协同制造系统的子任务协作的时序约束问题。
The networked cooperative manufacture among
enterprises can promote their competitive capacity and the first
step is to disassemble the project into several sub-projects.There
are priority constraints among the sub-projects and their
completion must follow a certain time sequence. Here gives a
new method to describe the constraints and calculate the exact
executing time area of each sub-project.The time sequence of the
sub-projects can be described by our defined before relation
R_(before) coupled with both sub-relations including serial before
relation R_(s-before) and parallel before relation R_(p-before). The
backward deducing arithmetic to calculate the executing time
areas of the sub-projects is raised. Moreover,the rules to
determine the disassembling granularity of the project are
proposed. Eventually, the practice proved that the method could
effectively solve the time-sequence constraint issue of the
sub-projects in the multi-agent based networked cooperative
manufacturing system.
出处
《机械工程学报》
EI
CAS
CSCD
北大核心
2004年第6期28-33,共6页
Journal of Mechanical Engineering
基金
国家863/CIMS主题(2002AA412610)
国家自然科学基金(59975079)
关键词
网络协同制造
目标分解
时序约束
Rbefore关系及其子关系
分解粒度
Networked cooperative manufacture
Project disassembly Time-sequence constraint
Before relation and its sub-relations
Disassembling granularity