摘要
江苏沙河抽水蓄能电站利用已建的沙河水库作下水库。沙河水库为综合利用水库,为确保蓄能电站的正常运行,协调沙河水库各用水部门的用水要求,并确保水库工程防洪安全及减少库区和下游的淹没损失,研究制定了其运行调度原则为:保证蓄能电站的运行不受破坏,保障生活供水。供水次序为先蓄能电站发电与生活供水,而后依次为工业用水与农业灌溉。
The existing Shahe reservoir, which is a multipurpose reservoir, is used as the lower reservoir for the Jiangsu Shahe Pumped-storage Power Plant. Insure the reliable operation of the Power Plant, and coordinate the require with water of the the departments of water utilization, and guarantee security that the project of the reservoir prevents flood and reduce the losses of flooding of the reservoir area and low reaches. discuss and make the operate dispatcher's principle of the plant: guarantee the oper ation of the Power Plant is not destroyed, assure the supply water for living. The sequence of water supply is that the Power Plant generating and water supply for living is prior, followed by water for industry and irrigation in order.
出处
《水力发电》
北大核心
2004年第5期59-61,共3页
Water Power
关键词
下水库
综合利用
运行方式
洪水调度
沙河抽水蓄能电站
lower reservoir
comprehensive utilization
operational mode
flood regulation
Shahe Pumped-storage Power Plant