摘要
通过对江西省郭家滩水电站橡胶坝泄流进行面流消能计算,确定挑角和坎高,为面流消能模型试验提供基本参数.
Based on the calculation of the submerged bucket dissipation of the flexible dam of Guojiatan hydropower station,the bucket angle and the bucket height were determined.It can put the primary parameters for the submerged bucket dissipation model experiment.
出处
《江西水利科技》
2004年第B05期51-53,60,共4页
Jiangxi Hydraulic Science & Technology
关键词
郭家滩水电站
橡胶坝
面流消能
挑角
坎高
Submerged bucket dissipation
Bucket angle
Bucket height
Submerged discharge
Guojiatan hydropower station.