摘要
介绍了 2 30kt/a合成氨技术改造和运行情况 ,分析了试生产期间出现的问题及处理措施。整个工程所有装置总体运行良好 。
A description is given of the technical renovation and operation of an ammonia plant with a capacity of 230,000 t/a, and an analysis in made of the problems arisen in its trial production as well as the measures taken to settle these problems. All units in the whole projects generally run well, achieving the goal of energy conservation, reduction in consumption and change in product variety.
出处
《化肥工业》
CAS
2004年第3期61-64,共4页
Chemical Fertilizer Industry