锦江水库溢洪道消能工的设计特点 被引量:1

Design features for the energy dissipator of spillway of Jinjiang Reservoir
下载PDF
导出
摘要 以锦江水库第二溢洪道消能工设计为例,针对溢洪道轴线与河道垂直,水流挑射入河床后,可能冲刷对岸并产生回流、壅高水位,影响其他建筑安全运行等情况,采取理论计算与水工模型试验相结合的方法,找到了一种设置消力墙、预挖消能坑的综合消能措施,较好地解决了溢洪道挑流消能后的防冲问题,且节省了资金.经现场开闸放水测试,消能效果良好,对其他设施影响很小,达到了预期的目的. The second spillway energy dissipator of Jinjiang Reservoir was used as the study case to analyze water current coupling, water level rising and damage caused by the abrasion erosion of a jet,trajectory current in case of the spillway axis perpendicular to the axis of the river. An energy,dissipating wall developed based on theoretical calculations and hydraulic modelling is presented in this article. This energy,dissipating measure with preliminarily excavating a dissipating pit has permitted the successful solution of the problems of water jet abrasion erosion. This measure underwent practical site testing. They have good results and less influence on other neighbouring facilities to be able to achieve the goal predetermined.
出处 《水利水电技术》 CSCD 北大核心 2004年第5期41-42,共2页 Water Resources and Hydropower Engineering
关键词 溢洪道 消能设计 锦江水库 spillway energy,dissipating design Jinjiang Reservoir
  • 相关文献

参考文献3

  • 1江门市水利水电勘测设计院.江门市锦江水库除险加固工程可行性研究报告[R].,2000..
  • 2水利部珠江水利委员会科学研究所.广东省江门市锦江水库除险加固工程第二溢洪道单体水工模型试验研究报告[R].,2000..
  • 3祁庆和.水工建筑物[M].北京:水利水电出版社,1986..

共引文献15

同被引文献3

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部