秦沈客运专线A14试验段软土路基加固技术研究 被引量:6

Study on consolidation technique for A14 testing section of soft soil roadbed at Qinhuandao-Shenyang passenger transport special railway line
下载PDF
导出
摘要 介绍了秦沈客运专线A14试验段软土路基工程设计施工情况。通过对各种地基处理路段沉降观测,探讨了软土路基沉降特征,推测出其最终沉降量和沉降速率,并分析了软基处理措施与沉降的关系。结果表明软土路基沉降受加荷影响很大;采用碎石和粉喷桩处理后地基沉降量比其它处理方法要小;在松软土地层,控制填土不是主要问题。 The design and construction situations of A14 testing section soft soil roadbed on Qinhuangdao-Shenyang passenger transport special railway line are introduced. The subsidence data are observed in the testing sections what were treated through different groundwork treatment measures. The soft soil roadbed subsidence feature is discussed; and the subsidence data and subsidence rate after engineering works are predicted in the roadbed after consolidation treatment according to test data. The relationship between soft soil groundwork treatment measures and subsidences is also analyzed. The researching results indicate: the soft soil roadbed subsidence is affected by the added load very much; the subsidence amount of soft soil roadbed what is treated with gravel piles or lime injected piles is less than other methods of treatment; it is not a key that the rate of filling soil is controlled in the loose and soft soil roadbed.
出处 《岩土力学》 EI CAS CSCD 北大核心 2004年第8期1283-1287,共5页 Rock and Soil Mechanics
关键词 软土路基 试验 客运专线 加固技术 soft soil roadbed experiment passenger transport special line consolidation technique
  • 相关文献

参考文献5

  • 1铁道科学研究院.秦沈客运专线铁路路基施工技术细则(试行)[M].北京:中国铁道出版社,2003..
  • 2铁道科学研究院.新建时速200公里客货共线铁路设计暂行规定[M].北京:中国铁道出版社,2003..
  • 3梁钟琪.土力学及路基[M].北京:中国铁道出版社,1996..
  • 4陈仲颐 叶书麟.基础工程学[M].北京:中国建筑工业出版社,1995..
  • 5何思明.基于弹塑性理论的修正分层总和法[J].岩土力学,2003,24(1):88-92. 被引量:35

二级参考文献1

共引文献46

同被引文献40

引证文献6

二级引证文献45

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部