龙滩水电站地下厂房通风空调系统设计 被引量:1

The design of ventilation and air-conditioning system for the underground powerhouse Longtan Hydropower Station
下载PDF
导出
摘要 由于龙滩水电站地下厂房洞室庞大,通风空调系统复杂且容量大。为此系统设计时在热负荷计算、气流组织、设备选择上采取了有针对性的措施,充分利用天然冷源,尽量减少总通风量,采用特殊节能空调设备,在满足电站温湿度要求的情况下,以达到节能的目的。 Due to the huge caverns of the underground powerhouse of Longtan Hydropower Station, the air-conditioning system is complex, with a lage capacity. Some special considerations, such as heat load calculation, air flow management, and equipment selection are carefully made. Through taking full advantages of nature cooling source, reducing the total ventilation quantity as far as possible, applying specially designed air-conditioning equipment, the objectives of energy saving shall be achieved while meeting the demands of temperature and humidity in the Station.
出处 《水力发电》 北大核心 2004年第6期62-64,共3页 Water Power
关键词 天然冷源 温湿度控制 通风空调 龙滩水电站 natural cooling source control of temperature and humidity VAC(ventilation and air conditioning) Longtan Hydropower Station
  • 相关文献

参考文献2

  • 1金峰.水电站厂房通风、空调和采暖[M].北京:水利电力出版社,1984..
  • 2单寄平.空调冷负荷计算方法[J].空调技术,1983,(1).