摘要 为迎接西气东输和LNG(液化天然气)的输入,我国东部地区正在建设一批大型联合循环电厂。为使建成后的电厂单位投资省、热效率高、占地少、投产后具有较好的效益,选择合适的机组轴系配置至关重要。文中对我国急需建设的大型天然气联合循环电厂机组的轴系配置进行充分的分析和比较,并推荐出最合理的轴系配置方式。 In East and South China coastal regions, a batch of large scale gas-fired combined cycle generating units will be built as animportant supporting power source with the natural gas of 'transporting gas from West to East' and the imported liquefied natural gas (LNG)as fuel. A good shaft system configuration of combined cycle generating unit means less capital cost, higher heat efficiency, fewer occupiedland and more economic benefit after commissioned, This paper makes the full analysis and comparison of shaft system configuration for thelarge scale natural gas-fired combined cycle units to be built soon and suggests the most appropriate shaft system configuration.
作者 何语平
出处 《中国电力》 CSCD 北大核心 2004年第8期7-9,共3页 Electric Power
关键词 天然气 大型联合循环电厂 机组轴系配置 natural gas large scale steam-gas combined cycle generating unit shaft system configuraion of unit
  • 相关文献

参考文献2

  • 1LeroyOTomlinson SeanMcCullough.单轴联合循环发电系统[R]..GE Power Systems,GER-3767C-CN[C].,..
  • 2西门子发电部.新西兰Otahuhu400MW联合循环(GUD)电厂[R].,1998..

共引文献1

同被引文献70

引证文献17

二级引证文献33

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部