摘要
某厂检修期间需将催化装置再生器上的旧烟囱拆除,安装新烟囱,场地狭小,吊装难度较大,通过制定合理的吊装方案,安全快捷地完成了任务。该吊装方案是:在再生器顶部标高40m的平台上设置一组长24m的A型推扒杆及相应的滑车组,利用卷扬机提升。文章介绍了吊装机具的设置以及旧烟囱拆除、新烟囱安装的方法和步骤。
The old chimney located at regenerator of catalytic equipment was needed to remove and a new one was needed to install during a factory's overhaul.But hoisting operation faced certain diffi-culty because of small work site.Through making suitable hoisting plan,the task was fulfilled safely and successfully.The hoisting plan was to set up an A shaped mast of24m long and a pulley block on the platform at the altitude of40m located on regenerator top;a cable hoister was applied to lifting.This paper introduces the setting up of hoisting device,the method and procedure of old chimney removal and new chimney installation.
出处
《石油工程建设》
北大核心
2004年第4期43-44,共2页
Petroleum Engineering Construction
关键词
催化装置
再生器
烟囱
吊装
catalytic equipment
regenerator
chimney
hoisting