湖积软土地基的处理方法 被引量:16

REINFORCEMENT METHOD OF LACUSTRINE SOFT SOIL FOUNDATION
下载PDF
导出
摘要 软土地基处理方法很多,不同方法的处理效果、费用、工期相差悬殊,往往不能兼顾。结合排水板(排水砂井)的逐级加荷法费用省、效果好,但工期较长。武山铜矿新尾矿库堆石坝施工中使用较大的单层荷载,以湖积软土地基孔隙水压力测试为主,结合其他测试方法控制堆载进度,既保证了地基稳定性,又使工期较短,达到了兼顾地基处理效果、工期和费用的目的,可供类似工程借鉴。 There are many engineering methods to reinforce soft soil foundation. For different methods, the effect, cost and construction period may be very different, and it is difficult to consider all the aspects well. The step-loading method combined with draining-board has advantages of low cost and good result to soft soils, but the construction period is quite long. In the engineering of rockfill dam for new tailing storage of Wushan copper-mine, a large single layer loading method was used to reinforce the lacustrine soft soil foundation. The data of pore water pressure of foundation together with other parameters were used to control the loading speed. The stability of foundation was kept and the construction period was shortened. With the presented method, the cost, effect and construction period can be well considered simultaneously.
出处 《岩石力学与工程学报》 EI CAS CSCD 北大核心 2004年第17期2998-3002,共5页 Chinese Journal of Rock Mechanics and Engineering
关键词 岩土工程 湖积软土 堆石坝 分级加荷 稳定性测试 geotechnical engineering, lacustrine soft soil, rockfill dam, step-loading, stability measurement
  • 相关文献

参考文献6

二级参考文献13

  • 1谢康和.双层地基─维固结理论与应用[J].岩土工程学报,1994,16(5):24-35. 被引量:122
  • 2谢康和,曾国熙.等应变条件下的砂井地基固结解析理论[J].岩土工程学报,1989,11(2):3-17. 被引量:156
  • 3冯光愈,程展林,鄢重新.高速公路软土地基处理研究[J].长江科学院院报,1996,13(4):37-40. 被引量:20
  • 4曾国熙 卢肇钧.地基处理手册[M].北京:中国建筑工业出版社,1988..
  • 5《地基处理手册》编写委员会.地基处理手册(第二版)[M].北京:中国建筑工业出版社,2000..
  • 6[6]钱家欢,殷宗泽.土工原理与计算(第二版)[M].北京:中国水利水电出版社,1995.
  • 7[1]<地基处理守则>编写委员会.地基处理守则[Z].北京:中国建筑工业出版社,1988.
  • 8蔡恩捷(译),道路土工软土地基处理技术指南,1989年,138页
  • 9曾国熙,地基处理手册,1988年,45页
  • 10交通部第一公路勘察设计院,公路软土地基路堤设计与施工技术规范,1997年,148页

共引文献35

同被引文献111

引证文献16

二级引证文献175

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部