摘要
网络计划优化技术中的顺序优化理论具有国际先进水平,已有十多年的历史,但因编程困难,始终未能和实际有效地结合起来。顺序优化的编程是相当复杂的,之所以复杂是因为它不仅包含顺序优化,而且还包含因顺序优化而带来的网络图的调整。本文就是针对这一情况,介绍了一种适合解决此类问题的方法。
Sequence optimization theory of optimal technology of network plan which has been of advanced level in the world for ten years has not been applied to practice for difficult pragraming. The programming of sequence optimization not only include sequence optimization, but also the adjustment of network chart is attributed to it. A method which is fit to solve a difficult technical problem like this is introduced in this paper.
出处
《运筹与管理》
CSCD
2004年第5期47-50,共4页
Operations Research and Management Science
关键词
运筹学
顺序优化
十字链表
算法设计
工序的重心
序偶亏值定理
行偶亏值定理
operational research
sequence optimization
orthogonal list
algorithm
core of working procedure
theorem of ordinal even lose which indicates delay in time limit for a project
theorem of line even lose which indicates delay in time limit for a project