针对湿式石灰石-石膏法脱硫工艺布置,对国内已运行及正在设计建设的200MW机组、300MW机组、600MW机组湿法烟气脱硫布置进行了归纳整理。并对采用该工艺的设备布置以及脱硫占地的影响进行了详细分析。结论是应根据工程具体条件及采用的设备对湿式石灰石-石膏法烟气脱硫提出占地及主要布置。
This article sums up the process layout of lime stone & gypsum desulphating method for 200?MW,300?MW and 600?MW generating units which have been in operation or under construction in China.Analysis is given on the equipment layout and land taking up.The conclusion is that design of lime stone & gypsum wet flue desulphating method should consider the project specific conditions and the equipment used.