摘要
介绍广西西沙联围海堤工程迎海面裁弯取直新堤土方填筑中存在的问题,分析广西海堤工程的特点,并提出切实可行的解决方案。
The authors introduce the problems existing in the earth filling for new sea dikes which are components of Xichalianwei project and shaped by intercepting bends, analyze the features of sea dike construction in Guangxi, and put forward a practicable and feasible proposal for settlement.
出处
《广西水利水电》
2004年第3期40-43,共4页
Guangxi Water Resources & Hydropower Engineering
关键词
土方填筑
裁弯取直
海堤工程
Sea dike construction
earth filling for new dike
blowing sand to fill sea