朝阳矿主、副井冻结基岩采用3 3m深孔减冲光爆法施工,冻结段外层钢筋混凝土井壁平均掘砌速度分别达104 2m/月和106m/月,为爆破界探索出了前所未有的实践成果,给出了冻结壁、冻结管爆破安全和冻结段整体钢模板高度的理论计算.
The main and auxiliary shaft freeze bedrock of Chaoyang Coal mine construction with 3.3m deep-hole reduction flush light demolish are described, average driving speed of outer layer R.C.wall of a well in freeze Section are 104.2m/month and 106m/month. It not only shows the achievements, but also shows the theory calculation of freeze wall of a well and demolish safety.
出处
《焦作工学院学报》
2004年第4期295-299,共5页
Journal of Jiaozuo Institute of Technology(Natural Science)