基于GA的工程项目时间-成本均衡理论研究 被引量:3

Study of a GA-based Theory for Time-Cost Tradeoff Problem in Construction Projects
下载PDF
导出
摘要  在简要介绍遗传算法机理和基本控制参数的基础上,就如何构造工程项目时间-成本均衡遗传算法的染色体、适应值和群体规模等参数进行了分析,并就如何进行交叉和突变操作作了介绍.构建了工程项目时间-成本均衡遗传算法.发展了现有工程项目资源优化理论,根据文中理论编制的计算机软件,可在工程项目管理实践中推广使用. Firstly, the basic concepts and control parameters of Genetic Glgorithm (GA) are introduced in the paper. Secondly, a method of forming the chromosome of GA for time-cost tradeoff problem in construction projects is suggested. Thirdly, rules for determining the fitness value, as well as the population size, are invented and such skills as crossover and mutation are presented in detail. And finally, a GA-based theory for time-cost tradeoff problem in construction projects is summarized and the computerized system based on this method can be used in practice.
作者 王忠伟
出处 《中南林学院学报》 CSCD 2004年第5期61-65,共5页 Journal of Central South Forestry University
关键词 工程项目 时间-成本均衡 遗传算法 资源优化分配 construction projects time-cost tradeoff GA optimal resource distribution
  • 相关文献

参考文献22

  • 1PMI. Potential Research Topics[J/OL]. http:/ /www.pmi.org/info/pp-ResearchEventSandConf.asp,2002-07-10.
  • 2Siemens N. A Simple CPM Time-Cost Tradeoff Algorithm[J]. Management Science,1971,18(3B):354-363.
  • 3Slowinski R, Weglarz J. Solving the General Project Scheduling Problem with Multiple Constrained Resources by Mathematical Programming[A]. Proceedings of 8th IFFY Conference on Optimization techniques[C]. Berlin:Springer-Verlag.278-289.
  • 4Law A M, Kelton W. Simulation Modeling and Analysis[M]. New York: 2ndEd. McGraw-Hill,1990.
  • 5Holland J H. Adaptation in Natural and Artificial Systems[M]. Michigan: University of Michigan Press, Ann Arbor, MI, 1975.
  • 6De Jong, K A. An Analysis of the Behavior of a Class of Genetic Adaptive Systems[D]. Doctoral Dissertation, University of Michigan. Dissertation Abstracts International. University Microfilms,1975.76-9381.
  • 7Goldberg D E, Deb K. A Comparative Analysis of Selection Schemes Used in the Genetic Algorithms. Foundation of Genetic Algorithms[M]. San Mateo, Ca:Morgan Kaufman Publishers,1991.69-93.
  • 8Goldberg D E. Genetic Algorithms in Search, Optimization and Machine Learning[M]. USA: Addison-Wesley,1989.
  • 9Merkle L D. Analysis of Linkage-friendly Genetic Algorithms[D]. Ph.D. Dissertation. Air Force Institute of Technology, 1996.
  • 10何耀华,杨道红,华贲,李志红.基于智能集成的综合优化方法[J].中山大学学报论丛,1997(5):162-166. 被引量:1

二级参考文献56

共引文献127

同被引文献14

  • 1王忠伟.挣值管理方法在林业工程项目中的应用研究[J].森林工程,2004,20(5):36-38. 被引量:10
  • 2BabuA J G, Suresh N. Project management with time, cost, and quality consideration[J]. European Journal of Operational Research, 1996,88 (2) : 320-327.
  • 3Messac A. Physical programming: Effective optimization for computational design [J]. AIAA Journal, 1996, 34(1) : 149-158.
  • 4Messac A, Batayneh W M, Ismail Y A. Production planning optimization with physical programming[J]. Engineering Optimization, 2002,34 (4): 323-340.
  • 5Gardiner P D, Stewart K. Revisiting the golden triangle of cost, time and quality: the role of NPV in project control, success and failure[J]. Int J of Project Management,2000. 251-256.
  • 6Khang D B, Myint Y M. Time, cost and quality trade-off in project management: A case study[J]. Int J of Project Management, 1999,17 (4): 249-256.
  • 7LAW, A.M. and W. Kelton. Simulation Modeling and Analysis, 2nd Ed. McGraw_Hill, New York, USA, 1990.
  • 8Goldberg, D.E. and Deb, K. A Comparative Analysis of Selection Schemes Used in the Genetic Algorithms. Foundation of Genetic Algorithms. Morgan Kaufman Publishers, San Mateo, Ca, 1991:69-93.
  • 9Patterson J H, Huber D. A Horizon-Varying, Zero-One Approach to Project Scheduling[J]. Management Science,1974,24(6):990-998.
  • 10Patterson J H, Roth G W. Scheduling a Project under Multiple Resource Constraints: A Zero-One Programming Approach[J]. AIIE Transactions,1976,26(4):449-455.

引证文献3

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部