摘要
对一座在建水库电站在枯水期的运行同样必须进行水库优化调度。在水库已有日调节能力,水量损失不大的情况下,让水位控制在某个较高位置上运行时,电站将取得最佳发电效益。
It is imperatie optimally to control the operation of generating units in a reservoir under construction during dry seasons, i. e., to get the best benefit of the units by means of controlling the water level of the reservoir at a higher level under the condition of the reservoir having the capacity of daily regulation and low loss of water discharges.
出处
《江西水利科技》
1993年第2期138-142,共5页
Jiangxi Hydraulic Science & Technology
关键词
水库
发电
机组
最佳化
Reservoir under construction
Dry season
Optimally control
The best benefit