摘要 通过对三个工程实例中70个点位分别采用简单平差法和最小二乘法(间接平差法)所得高程的比较研究,发现两者不符值在闭合环线上表现为"首尾小,中间大";不符值的平均值远小于"二等"变形测量中变形点高程中误差限值,最大不符值也仅有"一级"基坑环境沉降警戒值的1.2%.因此认为:基坑工程环境沉降监测可以采用简单平差法进行成果处理. The study is carried on 70 nodes belonging to three practical leveling networks, and the heights of each node determined by the Simplified Error Adjustment and the Least Squares Method are compared. The results show that the height difference on initial and termination nodes in the leveling loops is smaller than the ones on the mid-loop nodes. However, the difference is tiny when it is compared with the Error Limitation stipulated in the National Code for Deformation Survey, and the maximum difference only accounts for 1.2% of the Alarming Limitation in Pit Construction Code. Thus, that the Simplified Error Adjustment may be used for settlement survey caused by pit construction is suggested.
出处 《华中科技大学学报(城市科学版)》 CAS 2004年第3期46-50,共5页 Journal of Huazhong University of Science and Technology
关键词 基坑 沉降监测 简单平差法 间接平差法 pit settlement error adjustment least squares approach precision
  • 相关文献

参考文献4

  • 1[1]GB 50026-93,工程测量规范[S].
  • 2JGJ/T8-97.建筑变形测量规程.[S].,..
  • 3於宗俦 鲁林成.测量平差基础(增订本)[M].北京:测绘出版社,1984.453-467.
  • 4[2]GB 50202-2002,建筑地基基础工程施工质量验收规范[S].

共引文献39

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部