摘要
根据仙女湖码头工程地形、地貌及地质条件 ,提出了一些行之有效的施工程序和施工技术 ,经工程建设与施工的检验 ,能够满足施工要求和工程要求 。
According to the topography,geomorphy and geology conditions of the Xiannühu dock project, some available and new construction procedures and techniques are put forward.Through checking up by construction and supervision, these new construction procedures and techniques can meet the demands of construction.At the same time, these new procedures and techniques provide new construction methods and references for other project construction. It is worth to popularize and spread.
出处
《三峡大学学报(自然科学版)》
CAS
2004年第5期420-423,共4页
Journal of China Three Gorges University:Natural Sciences