摘要
结合山西铝厂三期工程实例 ,通过分析 2 7跨门型轻钢结构厂房施工中出现的技术难题 ,提出了解决的方法 ,对控制工程质量、保证工程进度。
Combined with the 3rd project in Shanxi Aluminum Plant the technical difficulties encountered in construction of large-span portal frame light steel structure industrial building are analyzed; at the same time corresponding resolving measures are proposed in order to ensure engineering schedule, control construction quality and reduce cost.
出处
《山西建筑》
2004年第21期88-89,共2页
Shanxi Architecture
关键词
门型轻钢结构
变截面
H型钢
portal frame light steel structure, variable cross-section, H section steel