摘要
工程网络技术随着计算机的普及已越来越广泛地在建筑施工计划管理中得到应用。但由于高层建筑层次多,内容复杂,若将其施工计划反映在一张施工网络计划图上显得繁杂且不明了。本文根据多年在工程实践中,对分级网络计划图在高层建筑施工中的应用作了进一步探讨,提出了根据不同工程特点如何绘制分级网络图的原则与方法,并取得一定的社会和经济效益。
Engineering network techniques have been used widely in construction planning and management. Because of more floors and complication of tall buildings, it is not concise that construction planning is reflected in one construction network planning chart. According to many years of engin- eering experiences, a step is taken further to discuss the application of the graded network planning chart in construction of high-rise buildings. The principal and method of drawing the network chart is given according to different engineerings and it brings some social and economic welfare.
出处
《燕山大学学报》
CAS
2004年第6期557-560,共4页
Journal of Yanshan University