摘要
认真改革吊盘、吊笼、模板、投光灯、翻矸装置和井盖门等凿井辅助设备,使主、副、风3个立井平均月成井66.2m。
Due to the proper improvements of shaft sinking stage, cage, form, projector light, refuse discharge device, shaft cover and other shaft sinking auxiliary equipments, the shaft sinking operations of main shaft, auxiliary shaft and ventilation shaft in Shantaizi Mine have been reached an average month shaft completed rate of 66. 2m.
出处
《煤炭科学技术》
CAS
北大核心
1993年第10期13-15,共3页
Coal Science and Technology